Yamazumi Workload Chart
Stack work elements by station or operator, compare workload with takt time and identify overload, waiting and opportunities to rebalance work.
Stack work elements by station or operator, compare workload with takt time and identify overload, waiting and opportunities to rebalance work.
Stack work elements by operator or station and compare each load with takt time.
Use Yamazumi to reveal overload, idle time, uneven work content and balancing opportunities.
Yamazumi visualises element-level workload against demand. It is most useful when standard work elements and observed times are reliable.
Stack work elements by station or operator, compare workload with takt time and identify overload, waiting and opportunities to rebalance work.
Confirm takt and standard work scope
Break work into observable repeatable elements
Measure representative element times
Stack elements by current assignment
Rebalance within precedence, skill and ergonomic constraints
Three operators have workloads of 47, 68 and 39 seconds against a 60-second takt. Reassigning inspection and packaging elements creates 52, 53 and 49 seconds.
Balancing unstable or undefined work
Using averages that hide recurring variation
Moving tasks without precedence or ergonomic review
Treating takt time as a personal performance target
Prepare takt or target cycle, work elements, observed times, station assignment, sequence and constraints.
The module produces stacked workload chart, overload visibility and alternative balanced assignments.
No. Treat the output as a structured engineering and improvement aid. Verify source data, assumptions, safety, quality, legal requirements and local process conditions with competent responsible people before implementation.