PDCA Improvement Cycle
Plan an improvement hypothesis, record execution, compare actual results with the target and decide what to standardise or revise.
Plan an improvement hypothesis, record execution, compare actual results with the target and decide what to standardise or revise.
Manage improvement as a controlled Plan–Do–Check–Act cycle with evidence and follow-up actions.
Use PDCA when a change must be tested, measured, evaluated and either standardized or corrected.
PDCA separates prediction from evidence. The Check phase tests whether the intervention caused the expected result before the change becomes a standard.
Plan an improvement hypothesis, record execution, compare actual results with the target and decide what to standardise or revise.
Plan the problem, baseline, target and hypothesis
Do the smallest safe trial and record deviations
Check data against the expected result
Act by standardising, adapting or abandoning the change
Start the next cycle from the remaining gap
A team expects a new material route to reduce walking from 420 to 250 metres per shift. The trial reaches 265 metres, reveals one obstruction and is revised before standardisation.
Starting with actions before defining a target
Treating Do as full rollout rather than a test
Checking opinions instead of agreed evidence
Standardising despite an unverified result
Prepare problem, baseline, target, hypothesis, actions, owner, due date and measured result.
The module produces PDCA record, action status, target comparison and Act decision.
No. Treat the output as a structured engineering and improvement aid. Verify source data, assumptions, safety, quality, legal requirements and local process conditions with competent responsible people before implementation.